Report day summary

24.0 h observed, including 5.0 h confirmed NPT. 3.4 h drilling ILT against the 35 ft/h benchmark.

Calculated from validated source events · 100.0% report-day coverage

Benchmark-adjusted efficiency

Shown only when the full day is observed, all time is classified, and the selected drilling benchmark covers every productive minute. This scenario metric is not a universal field-efficiency score.

Not available

86.8% of productive time benchmark eligible

Confirmed NPT

Only time explicitly classified NPT in the report; multiplied by the rig-rate assumption for cost.

5.0 h

$25,000

Drilling ILT

Eligible drilling duration less footage / selected benchmark. Trip ILT remains unknown.

3.4 h

Against 35 ft/h

Hole depth

Last available hole measured depth, not drill-bit position.

6,590 ft

Latest observed measured depth

Excess CO₂

(NPT + qualified ILT) × incremental fuel × carbon factor. Unknown fuel leaves carbon unavailable.

5.1 t

501 gal modeled fuel

Depth and time

— Observed hole depth— Below benchmark▰ NPT
6,1006,2256,3506,4756,600
00:00–03:00 · drilling · productive03:00–05:00 · drilling · productive05:00–06:00 · circulating · productive06:00–10:00 · rig repair · npt10:00–13:00 · drilling · productive13:00–14:00 · waiting · npt14:00–17:30 · drilling · productive17:30–19:00 · bha change · productive19:00–24:00 · drilling · productive
00:0006:0012:0018:0024:00
Measured hole depth (ft) · local report-day time
06:00–10:00NPT

rig repair

Unplanned mud pump repair delayed drilling for four hours.

Hole depth start / end
6,250 / 6,250 ft
Duration
4.0 h
Drilling ILT
Not available
Time exposure
$20,000

SYNTHETIC_DDR_DEMO.csv · Page unavailable

PUMP #2 LINER SEAL FAILED, REPLACE, TEST 4H

ev-04 · high extraction confidence

Event log 9 of 9

TimeOperation / exact source excerptClassHoursILT (h)Source
00:00–03:00drilling

DRILL 6100-6210', WOB 24klb, ROP 36.7

Productive3.00.0

ev-01

03:00–05:00drilling

DRILL HARD STRINGER, ROP 20ft/hr

Productive · ILT2.00.9

ev-02

05:00–06:00circulating

CIRC/COND MUD

Productive1.0Not available

ev-03

06:00–10:00rig repair

PUMP #2 LINER SEAL FAILED, REPLACE, TEST 4H

NPT4.0Not available

ev-04

10:00–13:00drilling

DRILL AHEAD 130', ROP 43ft/hr

Productive3.00.0

ev-05

13:00–14:00waiting

W.O. PARTS CONFIRMATION 1HR

NPT1.0Not available

ev-06

14:00–17:30drilling

DRILL 60' IN 3.5 HOURS, LOW ROP

Productive · ILT3.51.8

ev-07

17:30–19:00bha change

POOH BHA SERVICE / BIT CHANGE

Productive1.5Not available

ev-08

19:00–24:00drilling

DRILL 150' IN 5H

Productive · ILT5.00.7

ev-09

Time exposure

Total scenario$41,786
Rig day rate
$120,000
Drilling benchmark
35 ft/h
Incremental fuel
60 gal/h

Mantle · SYNTHETIC DEMO — illustrative events, not actual field records. Classifications come from the report. Flat hole depth alone does not prove downtime. ILT, financial exposure and CO₂ are scenario estimates, not audited losses or measured emissions. Human review required.

Source warnings (4)
  • This is a synthetic demo, not a source-verified industry report.
  • Drilling ROP benchmark and rig day rate are editable scenario assumptions.
  • ILT cannot be evaluated for every productive interval. Trip speed requires separate bit/string movement; hole depth is insufficient.
  • Benchmark-adjusted efficiency is unavailable because the drilling benchmark covers only 86.8% of productive time. Unobserved or unbenchmarked time is not assumed to meet target.